Define the question before choosing the method
Prototypes go wrong when the method is chosen before the question. A printed housing answers a fit question in a week and answers nothing about porosity. A billet-machined part answers a fit and function question and tells you nothing about draft or flow. A soft-tool casting answers castability at low volume but costs more than either.
The useful sequence is to write down what has to be learned, then pick the cheapest method that can learn it. Most projects need two rounds: a shape round to check fit, and a process round to check the casting.
- Write the question first: fit, function, or castability
- Cheapest method that answers it wins
- Two rounds is normal: shape, then process
- Do not pay for castability before the shape is settled
The options compared
The table is the practical comparison for a part in the 100 g to 3 kg range. Lead times assume a competent supplier and a settled CAD model.
| Method | Lead time | Cost | What it proves |
|---|---|---|---|
| CNC from billet | 5–12 days | Low–medium | Fit, function, some surface |
| 3D printing (SLA/SLS) | 2–5 days | Low | Fit and appearance only |
| Soft tool casting | 2–4 weeks | Medium | Castability at low volume |
| Sand casting pattern | 3–5 weeks | Medium | Castability, coarse tolerance |
| Production tool T1 | 4–8 weeks | High (tool) | Everything, at full cost |
| Bridge tool | 3–5 weeks | Medium–high | Castability near production |
Costs scale with size and tolerance. A CNC prototype that holds a machined tolerance can be more expensive than a soft-tool casting.
CNC from billet: the default prototype
Machining from billet gives a metal part with the right alloy, the right mass approximately, and machined tolerances. It is the best way to check fit, function, assembly and — importantly — how the part feels to a customer. What it cannot show is draft, parting line, ejector marks, flow lines or porosity, because none of those exist in a machined part.
The trap is treating a machined prototype as a design freeze. A billet part can have vertical walls, sharp internal corners and zero draft because the cutter does not care. Those features become tooling problems later, and the DFM review should run on the prototype model before the tool is quoted.
- Best for fit, function and customer presentation
- Shows nothing about draft, parting line or porosity
- Run the DFM review on the prototype model
- Watch the mass: a billet part can be heavier than the casting
Soft tooling and bridge tooling
Soft tooling — aluminum or low-hardness steel dies, often with simplified ejection — produces real castings at low volume. It is the right choice when the project needs to test castability, finish or a leak-critical feature before committing to a production tool. Tool life is limited, typically a few thousand shots, and the process window is narrower than a production die.
Bridge tooling sits between soft and production: a real die built to a lower life target, used to supply early production while the main tool is built. It is common in automotive programs with a long validation phase.
- Soft tool: real castings, limited life, narrower window
- Use it when castability or leak tightness is the question
- Bridge tool: early production volume before the main die
- Budget for the die life you actually need
When to go straight to the production tool
If the design is mature, the volume is committed and the only open question is whether the tool works, a production tool with a T1 sample is the fastest route. The tool lead time is 15–25 days from a released design, so the T1 arrives sooner than many prototype programs finish.
The risk is that a design change after T1 costs steel. That risk is managed by the DFM review, not by building a soft tool: a thorough review is cheaper than a prototype and catches the problems a prototype would have shown.
- Mature design plus committed volume: go to production tool
- Tool lead time 15–25 days, T1 3–5 days after tryout
- DFM review manages the change risk more cheaply than a prototype
- Prototype and tool can run in parallel if the design is stable
Prototype options: where to go next
The prototype method follows from the question, not from the budget alone. Send the CAD model and say what the prototype has to prove and the review can recommend the cheapest route that answers it.